Painting & tiling


There's been a lot of progress over the last couple of weeks. Most of the walls have been plastered and the painting has started. The kitchen's being prepared ready for installation, around a week from now.










The limestone floor tiles are being laid in the kitchen.








The brick wall in the dining area is almost complete and the stairs have been ordered. 


The portakabin has been removed from the back garden, in anticipation of the utility room being finished at the side of the house. So the TV room has become the new site office.










Upstairs






Family bathroom






Bedroom 1



Master bedroom








Bedroom 3

Bedroom 3

Bedroom 2